Hosting : Phase n°1 finished to 100%

Lesia on Saturday, November 26th 2005

Friday: 

10:00 am: We begin to instal the new bay in the Redbus Data Center.

06:00 pm: We finished the premilinary works, we return to the hotel while waiting for midnight. 

Saturday: 

00:00 pm: Return to Redbus, 2 persons put off the servers while 2 other prepare to put back them.

00:35 am: We cut the principal servers. The relocation stars, fortunately the 2 locales are located in the same building in 2 differents operator. 

2:00 am: The websites are reactivated but we have big slowness problems. The system of traffic forwarding poses problem. We decide to change of forwarder. 

03:30 am: The websites are normally accessible, average time of calculation of the pages of our test site: 0,07 seconds. We get back in smile. 

04:45 am: All is finished we return to the hotel under the snow. The office of Ajaccio closed its doors at 04:00 am. 

10:45 am: Gillian carries out a control on managements we had forgotten to reactivate them. 

10:48 am: Managements are open 

PS: We are currently blocked in the Orly airport because of snow.